don yard leads phase 1 / phase 2
Phase-by-phase execution of new lead tracks and realignments.
don yard leads phase 1 & phase 2
advancing don yard track infrastructure
status: completed
TTR constructed two new lead tracks for into GO Transit’s Don Yard Layover Facility and Harbour lead. As construction manager, TTR supervised all construction activities, inclusive of labour and materials associated with the required works.
TTR managed the following activities as part of the contract with GO Transit:
Preparation of sub-ballast for both lead tracks to required grade for application of twelve (12”) of clear granite stone ballast
Removal and disposal of any and all extraneous soils and or soil materials
Construction of approximately 3,700 track feet of new 115lb rail for new leads
Installation of new #2 THW end plated track ties for new leads, closure and upgrade section
Installation of two (2) new #8 115lb LH & RH SGM Crossovers, inclusive
Removal and closure of an existing #11 switch with new 115lb rail and new track ties
Removal and closure of an existing #8 switch to be relocated approximately 200 feet on the Harbour Lead
Removal and relocation of a road crossing on the Harbour Lead
Installation of relocated road crossing
Surfacing and lining of all new track construction
Commissioning of all new track construction

Railway maintenance Services We've provided
TTR in action
Toronto Terminals Railway has delivered a wide range of railway maintenance projects including track repairs, switch upgrades, signal maintenance, and emergency response services. Each project reflects our commitment to safety, efficiency, and keeping rail systems running smoothly in all conditions.
Choose a project to learn more.
Have Questions, want to know more?
Have questions or want to learn more about Toronto Terminals Railway, positions, or what we do? We're here to help! Reach out anytime, we're happy to provide the info you need and guide you through the opportunities we offer.